Peak Lopping Explained

Peak load lopping also known as ‘peak load shaving’ & ‘load sharing’, is the used when the GRID supply can’t be increased due to cost or location and you need more power than is available.

When the more power is required and the GRID can’t or won’t supply the need, then the only alternative is an additional generator power source that operates in synchronisation with the mains power supply, to deliver additional power beyond the peak demand of your existing GIRD supply.

Using an automatic installed generator to provide the additional power supply when you need, is the most cost effective way to supplement mains GRID power either on a temporary basis during periods of high demand or permanently without the horrendous cost on your DNO provided additional capacity. Power Continuity is here to help.

For example:
If a site only has an 80amp 3 phase supply and should the site be likely to operate above 80 amps 3 phase then the automatic installed generator will start up to prepare to take the additional load automatically, supporting the GRID supply with additional ‘on site power’ beyond the maximum GRID supply.

Both the generator and the GRID supply will provide power to your site, working together in parallel.

That would allow the site to have power of 80amps + 180amps = 260 amps whenever required, without the cost of additional GRID cabling or DNO connections.When the site requirement is likely to drop below 80 amps the generator will stop and the site continues on GRID supply. All operated automatically, fully synchronised, seamless.

In the UK, G59 is the regulatory standard surrounding the connection of any form of generator device to run ‘in parallel’ or ‘synchronised’ with the mains electrical utility grid (National Grid). Power Continuity will carry out the G59 configuration of the existing site LV panels and the specification of the Load Lopping Panel will need to be built and configured, site specific; all controlled by Programmable Logic Controllers (PLC).

The G59 automation will allow a fully automatic load lopping system by means of the electronics and breakers within the bespoke panel built by Power Continuity. We will also therefore have to add G59 capability to the Generator for complete synchronisation of the load lopping system.

For a large proportion of the working day you may require load lopping but at weekends, the existing GRID power supply may be sufficient; then you’ll be supported ONLY by GRID power. Your local UK Distribution Network Operator (DNO) will advise you as to whether their costs for additional electrical power will be prohibitive or whether Load Lopping is more cost effective.

Should you go down the Load Lopping route, your DNO will provide the application paperwork and Power Continuity can help you fill it out prior to submission. Upon installation, the local DNO will wish to be present when the system is tested and commissioned, to ensure it meets the latest DNO & GRID regulations. Once sign off you’re ready to go.

There is nothing onerous about Load Lopping. Both the GRID and your local DNO are fully aware of thousands of sites across the UK that use their own generators to provide additional power.

If you require any assistance, Power Continuity can help YOU.
We’re here 24/7 to support our UK customers.

Call 0845 05 8455 and ask to speak with one of our engineers.

G59 Peak Lopping Generator Power System

Talk to Us: